Immagine frontale della Stazione Elettrica di Carcarello

Construction of an electrical substation near Viterbo (Italy)

Area: High voltage

Year: 2025

Scope: a 150/30 kV user substation in Tarquinia (Viterbo)

Altenia has built a 150/30 kV user substation in Carcarello – Tarquinia (VT), designed to connect two photovoltaic plants located in northern Lazio. The project was carried out on behalf of a renowned multinational company operating in the industrial and energy sectors, a global leader in metallurgy and power generation.

Activities: civil, electrical works and HV transformer installation

Following the signing of a turnkey EPC contract, Altenia carried out all the activities required to complete the HV/MV substation. The works, which began in July 2024, were completed with the energization of the plants within the contractual delivery date.

The main activities included:

Design:

  • development of the complete executive design of the HV/MV substation and detailed engineering;

Civil works:

  • construction of station buildings, transformer foundations, oil collection tanks, concrete perimeter wall, trenches, and water drainage systems;

Electrical works:

  • LV and MV connections, supply and installation of transformers and MV switchgears, HV busbar system, CTs, VTs, disconnectors, and circuit breakers;

HV transformer installation:

  • technical assistance for installation, assembly, and commissioning of the transformer supplied by the client;

SPCC installation:

  • Implementation of remote protection and control systems (SPCC), in line with the latest standards and Terna’s technical requirements;

Final Testing & Commissioning:

  • execution of test and commissioning of all works, in full compliance with the client’s guidelines and applicable regulations.

Results: two photovoltaic plants connected for about 40 MWp

Thanks to Altenia’s contribution, the client successfully connected the photovoltaic plants to the High Voltage grid, achieving a total installed capacity of approximately 40 MWp.

Frontal photo of an electrical substation built by Altenia.

Share